With the influx of new wind power plant to be built in Norway over the next few years, many contracts will be signed. Our friends at Nexans have announced that they will be delivering cable infrastructure to Roan.

The Roan project, consisting of 71 turbines, and due to be erected by 2018, is the second largest of the six projects which together constitute the 1000 MW Fosen project. From April, Nexans will start delivering the approximately 200 km of cables needed to connect the turbines together, and to connect the wind power plant to the grid. Linka AS is responsible for installing the electrical infrastructure on Roan, and Johs J. Syltern AS is the responsible entrepreneur.

In the future, there’s not pipelines but the power grid which will deliver the energy to the industry and transport. We are happy that it is our friends at Nexans who are to deliver those cables at Roan. 

Tilbake

Relaterte nyheter:

06-10-17 Ånstadblåheia: status september
02-10-17 Fortum starter bygging av Sørfjord vindpark
29-09-17 Fortum: Final investment decision on Sørfjord wind farm
26-09-17 To fartøy skal installere over 50 kilometer med kabler på Triton Knoll vindparken
26-09-17 PEAB skal bygge Hitra 2 vindpark
26-09-17 Påtroppende sametingspresident om vindpark: – Grønn kolonisering

Om Norwea

Vind- bølge- tidevann

Norwea er en interesse- og lobbyorganisasjon som jobber for å fremme norsk fornybar energiproduksjon. Norwea  arbeider for å skape og opprettholde et modent og langsiktig vindkraftmarked i Norge. Vi arbeider også for en langsiktig utvikling av marin fornybar energiproduksjon som utover offshore vindkraft, inkluderer energiformer som bølge- og tidevannskraft. Les mer om Norwea...

NORWEA, Vind- Bølge-Tidevann
Wergelandsveien 23b,
0167 Oslo
post@norwea.no
Tlf. +47 47 34 93 48
© Copyright 2006 - 2012
All rights reserved.